Skip to main content

Benefits of traffic light synchronisation

Alicia Parkway corridor, located in Orange County, California, was part of Phase 1 of an inter-jurisdictional Traffic Light Synchronisation Programme (TLSP) in Orange County designed to increase mobility and overall drive quality while reducing fuel consumption and greenhouse gas emissions. By increasing average speeds and reducing travel times via the reduction in stops, the programme sought to reduce vehicle acceleration and deceleration events along the corridor; these have been identified as the leadin
January 27, 2012 Read time: 4 mins

Alicia Parkway corridor, located in Orange County, California, was part of Phase 1 of an inter-jurisdictional Traffic Light Synchronisation Programme (TLSP) in Orange County designed to increase mobility and overall drive quality while reducing fuel consumption and greenhouse gas emissions.

By increasing average speeds and reducing travel times via the reduction in stops, the programme sought to reduce vehicle acceleration and deceleration events along the corridor; these have been identified as the leading cause in greenhouse gas production.

The TLSP was funded through the Proposition 1B -Transportation Bond Program (Prop 1B) and for Alicia Parkway addresses the corridor's east-west segments on either side of Interstate 5 (I-5) - the main north-south freeway. During the weekday Alicia Parkway, a freeway-centric corridor, has traffic volumes in excess of 60,000 vehicles per day on its short spans near the I-5 freeway. After installing two 1763 Econolite Centracs Advanced Traffic Management System (ATMS) and several ASC/3 controllers, Alicia Parkway saw reductions in travel times (11 per cent), number of stops (33.3 per cent) and greenhouse gases (8,100+ lbs.). Moreover, estimated three-year fuel savings are projected to exceed 1.1 million gallons (based on 250 weekdays per year).

Project:
Alicia Parkway traffic light synchronisation: 11-mile corridor with 41 signalised intersections

Benefits:
• 1.1 million gallon fuel savings over three years
• 11% reduction in overall travel times
• Up to 75% reduction in number of stops
• 7% reduction in greenhouse gases
• Average commute speed increased by as much as 31%

Project outline

In April 2008, as part of Prop 1B and matching funds from Measure M (M1), 1768 Orange County Transportation Authority (OCTA) implemented a multiphase TLSP, addressing 153 miles (246.2km) of arterials and 533 intersections in the county. In the summer of 2009 work began on Alicia Parkway, which represents six agencies: five cities (Aliso Viejo, Laguna Hills, Laguna Niguel, Mission Viejo and Rancho Santa Margarita); and Caltrans. The 11-mile (17.7km) corridor includes 41 signalised intersections. Despite its suburban setting, this corridor experiences urban-level congestion.

Improvements for the Alicia Parkway TLSP included upgrades to traffic management systems, intersection traffic signal controllers, communication systems, and new optimised signal timing. For this ITS upgrade, two Econolite Centracs systems were installed - a physical installation in Laguna Hills, and a virtual installation in Mission Viejo. Additionally, several ASC/3 traffic controllers were installed, enabling immediate traffic signal coordination along the two major segments of Alicia Parkway: the west segment from Crown Valley Parkway to I-5, which includes 24 signalised intersections; and the east segment from Santa Margarita Parkway to I-5, which includes 17 signalised intersections.

A powerful ATMS was required as a turnkey solution that enabled enhanced system-wide control of signal controllers, operational monitoring, inter-agency sharing, system scalability and support. A powerful client-server ATMS application that provided seamless wide-area network communications using current workstations and IT tools, including the capability to communicate over both Ethernet fibre-optic and existing copper serial systems, was a prerequisite.

The ATMS also had to provide the system and support flexibility essential to stay within budget. In addition, it had to be configured in a virtual server environment to integrate with an existing IT system, as well as integration requirements of a new gigabyte fibre-optic Ethernet communications system.

Results

Before and after travel time studies were conducted on the two corridor segments for morning, midday, and evening periods during the weekdays for westbound and eastbound directions. Addressing the project objectives, the metrics compared for the study were travel time in minutes, number of stops, average speed and greenhouse gas production. In some instances, the number of stops reduced by 75 per cent during the morning and evening hours. Average speed increased by as much as 31 per cent. In addition, greenhouse gas emissions were reduced by 7 per cent.

Interestingly, the study validated the significance of dynamically monitoring signal timing and operations. As anticipated, there were several categories that showed little to no improvement, particularly in travel times and number of stops during the morning and evening commute through the Laguna Niguel, Aliso Viejo and Laguna Hills city segments. These three cities had previously deployed traffic signal synchronisation, using Econolite systems to optimise traffic flow. The synchronisation strategies and Econolite solutions were installed and proactively monitored by traffic engineering firm, Hartzog & Crabill under contract by these cities.

For more information on companies in this article

Related Content

  • Emissions reductions targets to have major impact on transport
    October 28, 2015
    As bold moves aimed at reducing greenhouse gas emissions have been introduced in California, David Crawford looks at the ramifications for transportation. California Governor Jerry Brown’s recent dramatic raising of the bar on emissions reduction policy for the state has won him praise from Japan, Australia, Europe and the secretariat of the critical UN conference on climate change being held in Paris in November/December 2015. His April 2015 executive order aimed at bringing emissions to 40% below 1990 lev
  • Harmonisation of Europe's ITS deployment still unbalanced
    January 31, 2012
    Dean Herenda, Chairman of the EasyWay project, talks about the progress made and the progress still to be made in harmonising ITS deployment across the European Union. "The deployment and use of ITS in road transport across Europe was and still is unbalanced" Although Europe can be proud of being home to some of the world's most advanced ITS solutions, the relative disparities between Member States of the European Union (EU) in terms of the extent and technological sophistication of deployments actually sta
  • Small toll agency adopts big city thinking
    December 5, 2014
    Andrew Bardin Williams looks at a novel option for new toll road authorities. While somewhat politically controversial, outsourcing has gained traction in the business world as a model worth investigating for its efficiency and cost saving benefits. Lean start-ups tend to employ independent contractors instead of full-time employees in an effort to remain flexible and avoid costs associated with pensions, retirement places, health insurance, office space and benefit packages.
  • TransCore wins contract on new HOV to Express lane conversion
    April 3, 2012
    California’s Santa Clara Valley Transportation Authority (VTA) has launched the first phase of its 290km conversion of high occupancy vehicle (HOV) lanes to Express Lanes, or commonly known as high occupancy toll (HOT) lanes, with TransCore serving as lead integrator for the project. The US$11.8 million programme comes at a crucial time in Silicon Valley as it prepares for an expected 38 per cent growth in population over the next 20 years and funding for transportation improvements is projected to grow at