Developing integrated transport networks

A major initiative in managing numerous transport networks as a single system has moved into a significant phase with design of sophisticated new ITS systems. Jon Masters reports. Detailed design work is under way on two pilot projects pursuing a common principle – that transportation can be made more efficient or effective if the various networks and modes of travel are managed as a whole system. This is the central tenet of the US Department of Transportation’s (USDOT) Integrated Corridor Management (ICM)
September 20, 2012 Read time: 6 mins
The San Diego ICM project focuses on a 20 mile stretch of Interstate 15 and adjacent arterial roads in California

A major initiative in managing numerous transport networks as a single system has moved into a significant phase with design of sophisticated new ITS systems. Jon Masters reports.

Detailed design work is under way on two pilot projects pursuing a common principle – that transportation can be made more efficient or effective if the various networks and modes of travel are managed as a whole system. This is the central tenet of the 324 US Department of Transportation’s (USDOT) Integrated Corridor Management (ICM) programme. ICM is now emerging from phases of research and modeling, into implementation and demonstration, the last of which will start when design completion leads to installation along two transport corridors in San Diego and Dallas.

These are the two locations selected for the ICM pilot projects. Eight transport corridors were originally the focus of the USDOT led ICM research, before three (in Minneapolis, Dallas and San Diego) were chosen for modeling the effects and benefits of ICM approaches. Headline results from the website of USDOT’s 0 Research & Innovative Technology Administration (RITA) include annual travel time savings of 740,000 person-hours in Minneapolis, a 10.6% improvement in travel time reliability in San Diego and a 10 year net benefit of $264M in Dallas.

Turning these simulated results into reality is now the crux of what’s being done by highway authorities in San Diego and Dallas. Meanwhile, the attentions of ICM leaders at USDOT and RITA are turning to dissemination and outreach programmes. Two guidance documents have been produced, on ICM analysis, modeling and simulation (AMS) and ICM implementation – all for the purpose of helping transportation agencies initiate and develop their own ICM projects.

Reaching out

“Initially there has been a lot of modeling done, partly because USDOT wants to convince others to come up with their own similar projects,” says 560 ITS America chief technology officer Nu Rosenbohm. “There are plenty of schemes under way involving technologies such as ATM (Active Traffic Management), but very few based on multi-agency approaches. We want agencies to continue pushing deployment of new technologies, but with principles of ICM added to system engineering for coordination and ultimately better effect.”

Plans to reach out to other ‘potential adopters’ identified by USDOT should benefit from having ITS America supporting the ICM programme, initially with a series of related events at state chapter meetings. These follow ITSA’s annual meeting in Fort Washington in May, where a workshop was convened to allow ICM team leaders from USDOT’s federal transit and highway administrations to give updates on progress with the programme, with ICM project representatives from San Diego and Dallas.

2023 Federal Transit Administration senior ITS engineer Steve Mortensen presented the ICM modeling results, explaining that extensive AMS work was enacted to determine the right combinations of strategies for particular locations and operational conditions. Going forward, the USDOT team will be measuring in detail to what extent the ICM projects are working: “We have commissioned independent evaluation analysis. Several high level hypotheses will be tested. For each we have a corresponding area of analysis and detailed test plans,” Mortensen says.

Extracting full potential

For San Diego, the technology being developed is a new ICM system for managing a 20 mile stretch of Interstate 15 in conjunction with arterial roads connecting with the highway in California. The ICM system will work with existing hardware and infrastructure including ramp metering traffic signals at intersections and an I-15 Express Lanes facility opened to the public in January 2012.

The I-15 Express Lanes features four lanes separated by a moveable median barrier that allows the number of Express Lanes to increase to three lanes in one direction to help traffic flow during peak travel periods and to relieve congestion. These lanes are free for vehicles containing more than one occupant and are used by a new high-frequency express bus system. Solo drivers are charged a fee on a per mile basis, calculated based on traffic conditions.

The ICM project is being coordinated by SANDAG – the 1789 San Diego Association of Governments –  for principal partners 3879 Caltrans, the three cities of San Diego, Poway and Escondido and two transit authorities: MTS and NCTD. Crucially, a strategic plan of actions is being formed for all to respond concertedly to traffic congestion and disruption from planned or unplanned events. This will be supported by a number of ICM subsystems making use of historic and real-time traffic data. With built-in business rules and algorithms, the subsystems will combine to provide a decision support system predicting traffic conditions and recommending appropriate actions on a user interface common to every ICM partner.

“This project says a lot about where we are right now,” says SANDAG senior transportation planner and ICM co-project manager Alex Estrella. “We already have a lot of sub elements and state of the art field equipment for traffic management in place, whereas financially, there is a need to get the most out of these existing assets. Through ICM we envision leveraging all facilities and ITS investments to maintain and maximize corridor capacity and efficiency. To do this we have to change the paradigm of the traditional stovepipe approach, changing from operation of individual systems to an environment of integrated management.”

A new paradigm

To do that, real-time operational data has to be collected to build understanding of how infrastructure and traffic management systems are performing holistically. At the same time the technical minds of the partner organisations have to be brought together to work with the data. “They understand the importance of good data. All have bought into the vision of ICM,” Estrella says. “Once they have the data, the paradigm changes. For example, presently our arterial networks get flooded every time there is an incident on the freeway. ICM will allow us to apply specific plans for the benefit of the corridor based on data. We will move from a reactive to proactive stance, anticipating problems with appropriate action plans.”

SANDAG and its partners are due to be switching their ICM system on in spring 2013 when it will begin to collect and crunch traffic data to give a nearly continuous breakdown of what’s happening on I-15, while building a complex and detailed model of how traffic ebbs and flows with time and events. This modeling and monitoring serves as a fundamental element of the ‘network prediction subsystem’ – the backbone of the decision support system advising what should be done at 15 or 30 minute intervals before a disruption occurs.

“This element of the ICM will be up and running in 2014 and will be enhanced to get better as the ICM project progresses,” Estrella says. “The key question is the process itself, the on-going coordination between the ICM partners to consistently review, revise and implement improved response action plans. Since traffic or congestion does not always behave in the same way, we are unlikely to get response plans exactly right from the start,  but we will have opportunity to gather the data and apply the model to tweak the system and responses.”

Related Content

  • Tolling is still stuck on the sidelines says ASECAP speaker
    August 19, 2015
    Geoff Hadwick attended ASECAP’s 2015 Study Days meeting in Lisbon and found a frustrated European tolling sector undertaking some soul searching. The international road tolling industry its failing to make it case and the sector is losing out to a range of other socio-political lobby groups according to International Bridge, Tunnel and Turnpike Association (IBTTA) chief executive Pat Jones. Speaking at the recent 2015 ASECAP Study Days conference in Lisbon, Jones issued a stark warning: “Tolling is still o
  • Chicago mayor unveils Vision Zero Action Plan
    June 13, 2017
    Chicago Mayor Emanuel has announced the city’s Vision Zero Chicago Action Plan, a multi-Agency approach which aims to improve traffic safety for all road users. The ultimate goal of Vision Zero is to reduce roadway crashes and eliminate traffic fatalities and serious injuries in Chicago by 2026. A dozen City departments and agencies have been working for months with traffic safety stakeholders to develop the Vision Zero Action plan, which covers the first three years of the effort and is based on the princi
  • Sorting sensible from shiny in tolling technology
    December 11, 2014
    Instead of always striving for the latest shiny toys Kevin Hoeflich of HNTB advises a 10-steps method for selecting the most appropriate technology. Amid the hype and razzmatazz surrounding the launch of Apple’s iPhone 6, the company also announced its new mobile payment system, Apple Pay. Built into the new iPhone 6, Apple Pay works at 220,000 merchants across America and is supported by major US banks and the big three credit card companies.
  • US ushers in reforms with new transportation bill
    November 9, 2012
    On behalf of ITS America, Paul Feenstra maps out implications and opportunities for the ITS industry. A critical milestone was reached last month when the US Congress passed, and President Obama signed, legislation reauthorising the nation’s surface transportation programmes, breaking a nearly three-year log-jam which had stymied critical transportation reforms and delayed much-needed infrastructure projects. The law, numbered P.L. 112-141 but known as MAP-21 (Moving Ahead for Progress in the 21st Century),