Norway to renovate 200 tunnels

The Norwegian Public Roads Administration (Statens Vegvesen) has to renovate 200 tunnels before 1 April 2019 to meet European Union safety requirements for tunnels. Norway’s Tunnel Safety Regulations 2007 apply to tunnels on state roads that are more than 500 metres long, of which Norway has 253. Thirty of these were built after 2007 and comply with the regulations, while only around twenty tunnels built after 2007 have been renovated. The authority will present an action program for the 2014-2017 period
August 12, 2013 Read time: 2 mins
The Norwegian Public Roads Administration (7446 Statens Vegvesen) has to renovate 200 tunnels before 1 April 2019 to meet 1816 European Union safety requirements for tunnels.

Norway’s Tunnel Safety Regulations 2007 apply to tunnels on state roads that are more than 500 metres long, of which Norway has 253.  Thirty of these were built after 2007 and comply with the regulations, while only around twenty tunnels built after 2007 have been renovated.  The authority will present an action program for the 2014-2017 period based on the National Transport Plan. It will include an overview of the tunnels and measures to be prioritised during the four-year period, says Lars Aksnes, Deputy Director General of the authority.

In many of the tunnels, only minor measures will be needed to meet the safety requirements, but some tunnels will require extensive measures, says Aksnes. These include power to emergency lighting, radio, fire-fighting equipment, new tunnel control technology, as well as the construction of new escape routes.

Related Content

  • November 4, 2014
    Norwegian study indicates benefits of average speed enforcement
    Evaluation of the crash effects of section control, or average speed enforcement, carried out at 14 sites in Norway has found a reduction of the number of injury crashes by between 12 and 22 per cent and a statistically significant reduction of the number of killed or severely injured road users (KSI) by between 49 and 54 per cent. Each section control site consists of a stretch or road between two speed cameras (four speed cameras at sites with bidirectional section control), both of which take pictures
  • July 26, 2013
    DG MOVE’s Christos Economou on the EU’s vision for road transport
    Christos Economou, Deputy Head of Unit dealing with land transport within the European Commission’s DG MOVE, describes a new framework for road charging in Europe to Jason Barnes. Within the European Union (EU), two Directives shape the legislative framework on road charging. Directive 1999/62/EC sets up a number of rules to make sure that national road charging schemes do not distort competition on the internal market or discriminate between hauliers. It is misleadingly called ‘Eurovignette’ after the comm
  • December 5, 2013
    Terrestrial solution to stellar shortcomings
    Inherent weaknesses in satellite communications are leading several countries to re-evaluate terrestrial-based backup systems. There is a tale frequently told in satellite navigation circles, of how landing systems at Newark Airport were disrupted by a truck driver using GPS jamming equipment as he drove along the New Jersey Turnpike. While there was no threat to flight safety as the interference to GPS reference stations being tested, the story highlights how apparently benign threats have the potential t
  • February 2, 2012
    Cooperative infrastructure - the future for tolling?
    Leading European tolling solution providers give a snapshot of how they think tolling's technological future will look