Temporary CCTV poses more challenges than permanent installations

Long-term roadworks pose particular problems for temporary surveillance installations. Converting the hard shoulder to a running lane, either full- or part-time, is the UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.
June 12, 2015 Read time: 4 mins
Frank Gearon installing feeds to the ‘Wonderbox’ for another temporary CCTV system.

Long-term roadworks pose particular problems for temporary surveillance installations.

Converting the hard shoulder to a running lane, either full- or part-time, is the 1841 UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.

Designing and implementing a number of these temporary CCTV monitoring systems for such projects is 7692 P&D Specialist Services. Current projects include 78 cameras along a 33km section of the M1 (Junctions 15-19), 109 cameras along 31km of the M3 (Junctions 2-4a) and 142 cameras on a 35km stretch of the M60 and M62 motorways around Manchester.

In April 2015 work started on a new section of ‘managed motorway’ along 23km of the M1 (Junctions 32-35a) where the hard shoulder is being converted into a running lane. As often happens with motorway projects during the construction phase the hard shoulder is inaccessible to motorists, meaning there are no emergency telephones and motorists have nowhere to stop safely and summon assistance in event of a breakdown or accident. “Before any construction work can start, temporary cameras have to be set up at regular intervals along the length of the work zone to monitor the area and detect breakdowns, accidents or incidents. That’s where the CCTV solutions we deliver come in,” says Frank Gearon, project manager of highway industry specialist P&DSS, “The aim is to deliver a real-time overview of the entire stretch of works and link all the images from the cameras back to the 24/7 manned control room.”

The company is a NICEIC contractor certified under the Highways Agency’s Sector Scheme Approval to carry out electrical works on the motorway network. At the start of this latest M1 project, it will initially deploy 30 CCTV cameras and that number will eventually double as the project progresses. Images from the cameras are streamed to a temporary monitoring station where they are also recorded, and because construction work cannot start until the cameras are working, Gearon says speed of deployment and system reliability are paramount.

“We use fibre optic cables to cope with the long distances involved, and AMG’s transmission equipment as it requires a smaller number of fibres which speeds splicing during installation. On some of the earlier projects we used AMG’s 3700 series and since 2013 we’ve used the AMG 9024– multi-service Ethernet switch (M-SES) series known as the ‘Wonderbox’.”

The ‘Wonderbox’ was designed to bridge legacy CCTV systems with new IP cameras and provides Layer 2 managed Ethernet functionality without having to involve third party products. By integrating low-speed serial data channels and alarm contacts, alongside analogue video, onto an Ethernet backbone it ‘bridges the gap’ between analogue and ‘IP’ technologies.

Due to the need to keep the roads open for traffic, such projects often run for 18 – 24 months so the CCTV systems have to withstand prolonged exposure to ambient weather conditions, vibration and dust so systems need to be very robust. 

However, that is not always enough as Gearon explains: “In major engineering projects like these, damage to cables and roadside equipment occurs frequently and there is a real risk of system failure, so on the M60/M62 project there was a requirement for a proprietary redundancy feature.

AMG was able to meet this need using the ‘X-ring’ to allow an unlimited number of M-SES units on each fibre loop, so sub-loops can be seamlessly added to provide redundancy protection in the case of a switch or fibre being damaged. And by integrating the dedicated video codec and RS232/RS485 into the MSES switch, video lag and control data is minimal.”

As the CCTV surveillance systems on the existing projects have operated over the winter period without a problem, the P&DSS/AMG solution appears to be lasting the distance.

For more information on companies in this article

Related Content

  • Convergence simplified
    June 19, 2012
    ComNet (Communication Networks) has introduced a new fibre-optic transmission product designed to aid in the transition from point-to-point systems to Ethernet network systems. The FVT/FVR10D1E Series are fibre-optic video transmitters and receivers that support digitally encoded video, serial data as well as 10/100 Ethernet. The company claims that the ComNet FVT/FVR10D1E is unique in that it provides 10-bit digitally encoded RS-250C short-haul quality video, serial data and 10/100 Ethernet on one single o
  • Improving urban traffic control in Atlanta
    January 27, 2012
    Hugh Colton, Georgia DOT details move to improve urban traffic control in the Atlanta area. With a significant proportion of traffic using freeways and toll-ways, along with a significant investment in roadway infrastructure, urban arterials are often the poor relation when it comes to ITS investment. Hitherto the primary means of Urban Traffic Control (UTC) has been the ubiquitous traffic signal. Many traffic signals still operate in a standalone mode and traffic detection is often broken, leaving the sign
  • UK organisations disagree on smart motorway ‘dangers’
    September 13, 2019
    A spat over how dangerous the UK’s all lane running (ALR) or ‘smart’ motorways are has broken out between Highways England and a leading motoring organisation. Smart motorways do not have hard shoulders, instead relying on emergency areas at intervals to provide refuge for stranded motorists. The AA recently highlighted Stationary Vehicle Detection, a Highways England report published in March 2016, which looks at how long it takes to identify a vehicle broken down in a live lane of smart motorway when s
  • Loop detection still has a part in traffic management
    March 2, 2012
    Bob Lees, co-founder of Diamond Consulting Services, on why the loop detector just refuses to go away. The more strident proponents of newer and emergent detection technologies are quick to highlight what they see as the disadvantages, and hence the imminent passing, of the humble inductive loop. The more prosaic will acknowledge that loops continue to have a part to play in traffic management, falling back on the assertion that it is all a question of application. And yet year after year the loop, despite