Temporary CCTV poses more challenges than permanent installations

Long-term roadworks pose particular problems for temporary surveillance installations. Converting the hard shoulder to a running lane, either full- or part-time, is the UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.
June 12, 2015 Read time: 4 mins
Frank Gearon installing feeds to the ‘Wonderbox’ for another temporary CCTV system.

Long-term roadworks pose particular problems for temporary surveillance installations.

Converting the hard shoulder to a running lane, either full- or part-time, is the 1841 UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.

Designing and implementing a number of these temporary CCTV monitoring systems for such projects is 7692 P&D Specialist Services. Current projects include 78 cameras along a 33km section of the M1 (Junctions 15-19), 109 cameras along 31km of the M3 (Junctions 2-4a) and 142 cameras on a 35km stretch of the M60 and M62 motorways around Manchester.

In April 2015 work started on a new section of ‘managed motorway’ along 23km of the M1 (Junctions 32-35a) where the hard shoulder is being converted into a running lane. As often happens with motorway projects during the construction phase the hard shoulder is inaccessible to motorists, meaning there are no emergency telephones and motorists have nowhere to stop safely and summon assistance in event of a breakdown or accident. “Before any construction work can start, temporary cameras have to be set up at regular intervals along the length of the work zone to monitor the area and detect breakdowns, accidents or incidents. That’s where the CCTV solutions we deliver come in,” says Frank Gearon, project manager of highway industry specialist P&DSS, “The aim is to deliver a real-time overview of the entire stretch of works and link all the images from the cameras back to the 24/7 manned control room.”

The company is a NICEIC contractor certified under the Highways Agency’s Sector Scheme Approval to carry out electrical works on the motorway network. At the start of this latest M1 project, it will initially deploy 30 CCTV cameras and that number will eventually double as the project progresses. Images from the cameras are streamed to a temporary monitoring station where they are also recorded, and because construction work cannot start until the cameras are working, Gearon says speed of deployment and system reliability are paramount.

“We use fibre optic cables to cope with the long distances involved, and AMG’s transmission equipment as it requires a smaller number of fibres which speeds splicing during installation. On some of the earlier projects we used AMG’s 3700 series and since 2013 we’ve used the AMG 9024– multi-service Ethernet switch (M-SES) series known as the ‘Wonderbox’.”

The ‘Wonderbox’ was designed to bridge legacy CCTV systems with new IP cameras and provides Layer 2 managed Ethernet functionality without having to involve third party products. By integrating low-speed serial data channels and alarm contacts, alongside analogue video, onto an Ethernet backbone it ‘bridges the gap’ between analogue and ‘IP’ technologies.

Due to the need to keep the roads open for traffic, such projects often run for 18 – 24 months so the CCTV systems have to withstand prolonged exposure to ambient weather conditions, vibration and dust so systems need to be very robust. 

However, that is not always enough as Gearon explains: “In major engineering projects like these, damage to cables and roadside equipment occurs frequently and there is a real risk of system failure, so on the M60/M62 project there was a requirement for a proprietary redundancy feature.

AMG was able to meet this need using the ‘X-ring’ to allow an unlimited number of M-SES units on each fibre loop, so sub-loops can be seamlessly added to provide redundancy protection in the case of a switch or fibre being damaged. And by integrating the dedicated video codec and RS232/RS485 into the MSES switch, video lag and control data is minimal.”

As the CCTV surveillance systems on the existing projects have operated over the winter period without a problem, the P&DSS/AMG solution appears to be lasting the distance.

For more information on companies in this article

Related Content

  • Integrate systems to reduce roadside infrastructure
    January 27, 2012
    David Crawford reviews promising current developments. Instrumentation of the road infrastructure has grown to become one of the most dynamic sectors of the ITS industry. Drivers for its deployment include global concerns over the commercial and environmental pressures of traffic congestion, the importance of keeping drivers informed throughout their journeys, and the need to reduce accident rates and promote the safety of all road users, for example by enforcing traffic safety rules.
  • Australia highway to receive smart tech 
    October 12, 2021
    Smart motorway tech will be installed between Pine River and Caloundra Road
  • Spot speed deterrent proved to be transient
    October 18, 2013
    As research and trials show the benefits of average speed enforcement - David Crawford reviews developments on two continents. August 2013 saw the switch on of the Australian State of Victoria’s latest combined point-to-point (P2P) average speed enforcement (ASE) and spot camera control system. Installed on the 27km Peninsula Link to the south-east of Melbourne, the system uses high-resolution automatic number plate recognition (ANPR) cameras and optical character recognition (OCR) technology developed b
  • M25 becomes UK’s smartest motorway
    April 11, 2014
    Final preparations are taking place for the M25 to become England’s first smart motorway, improving journeys and boosting the economy. Two sections of the motorway opening this month and next are between junctions 23 and 25 in Hertfordshire and between junctions 5 and 6/7 on the Kent/Surrey border. For the first time on a motorway scheme in England the hard shoulder will be used as a permanent traffic lane, with enhanced technology to manage traffic flow to improve the reliability of journey times.