Temporary CCTV poses more challenges than permanent installations

Long-term roadworks pose particular problems for temporary surveillance installations. Converting the hard shoulder to a running lane, either full- or part-time, is the UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.
June 12, 2015 Read time: 4 mins
Frank Gearon installing feeds to the ‘Wonderbox’ for another temporary CCTV system.

Long-term roadworks pose particular problems for temporary surveillance installations.

Converting the hard shoulder to a running lane, either full- or part-time, is the 1841 UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.

Designing and implementing a number of these temporary CCTV monitoring systems for such projects is 7692 P&D Specialist Services. Current projects include 78 cameras along a 33km section of the M1 (Junctions 15-19), 109 cameras along 31km of the M3 (Junctions 2-4a) and 142 cameras on a 35km stretch of the M60 and M62 motorways around Manchester.

In April 2015 work started on a new section of ‘managed motorway’ along 23km of the M1 (Junctions 32-35a) where the hard shoulder is being converted into a running lane. As often happens with motorway projects during the construction phase the hard shoulder is inaccessible to motorists, meaning there are no emergency telephones and motorists have nowhere to stop safely and summon assistance in event of a breakdown or accident. “Before any construction work can start, temporary cameras have to be set up at regular intervals along the length of the work zone to monitor the area and detect breakdowns, accidents or incidents. That’s where the CCTV solutions we deliver come in,” says Frank Gearon, project manager of highway industry specialist P&DSS, “The aim is to deliver a real-time overview of the entire stretch of works and link all the images from the cameras back to the 24/7 manned control room.”

The company is a NICEIC contractor certified under the Highways Agency’s Sector Scheme Approval to carry out electrical works on the motorway network. At the start of this latest M1 project, it will initially deploy 30 CCTV cameras and that number will eventually double as the project progresses. Images from the cameras are streamed to a temporary monitoring station where they are also recorded, and because construction work cannot start until the cameras are working, Gearon says speed of deployment and system reliability are paramount.

“We use fibre optic cables to cope with the long distances involved, and AMG’s transmission equipment as it requires a smaller number of fibres which speeds splicing during installation. On some of the earlier projects we used AMG’s 3700 series and since 2013 we’ve used the AMG 9024– multi-service Ethernet switch (M-SES) series known as the ‘Wonderbox’.”

The ‘Wonderbox’ was designed to bridge legacy CCTV systems with new IP cameras and provides Layer 2 managed Ethernet functionality without having to involve third party products. By integrating low-speed serial data channels and alarm contacts, alongside analogue video, onto an Ethernet backbone it ‘bridges the gap’ between analogue and ‘IP’ technologies.

Due to the need to keep the roads open for traffic, such projects often run for 18 – 24 months so the CCTV systems have to withstand prolonged exposure to ambient weather conditions, vibration and dust so systems need to be very robust. 

However, that is not always enough as Gearon explains: “In major engineering projects like these, damage to cables and roadside equipment occurs frequently and there is a real risk of system failure, so on the M60/M62 project there was a requirement for a proprietary redundancy feature.

AMG was able to meet this need using the ‘X-ring’ to allow an unlimited number of M-SES units on each fibre loop, so sub-loops can be seamlessly added to provide redundancy protection in the case of a switch or fibre being damaged. And by integrating the dedicated video codec and RS232/RS485 into the MSES switch, video lag and control data is minimal.”

As the CCTV surveillance systems on the existing projects have operated over the winter period without a problem, the P&DSS/AMG solution appears to be lasting the distance.

Related Content

  • UK’s M3 gets smart
    October 30, 2014
    Work begins shortly on the initial phase of a US$278 million project to improve the M3 between the M25 and Farnborough. The section between junctions 2 and 4a will become a smart motorway, adding a fourth lane in both directions in place of the hard shoulder and adding enhanced on-road technology to keep traffic moving safely and reliably, providing a boost for businesses and the wider economy. The road will also be resurfaced with a new, low noise material. The main works are due to be completed by the
  • Highways Agency plans to increase capacity of M4
    March 19, 2014
    The UK Highways Agency is holding a series of public exhibitions to inform road users, local residents and businesses about proposals to transform the M4 into one of the longest stretches of ‘smart motorway’ in England by 2021. The improvement, on a 32-mile stretch between junction 3 at Hayes in London, and junction 12 at Theale in Berkshire, would increase capacity, improve journey reliability and maintain safety. The proposals are part of the Government’s investment into England’s motorways and majo
  • Red X safety initiative launched in West Yorkshire
    September 16, 2016
    A red X response vehicle carrying automatic number plate recognition cameras is being used as part of the joint initiative between Highways England and West Yorkshire Police to raise awareness and improve compliance and safety. The initiative is part of Highways England’s ongoing campaign to raise awareness about smart motorways. CCTV footage has also been released showing an incident on the M1 near Wakefield where a van narrowly avoided striking a worker and a stationary vehicle when it travelled in a clos
  • New Hampshire plans for tomorrow’s communication
    August 21, 2017
    Someone once likened predicting the future to ‘nailing a jelly to the wall’. With ITS, C-ITS and V2X technology progressing at such a pace, predicting the future is more akin to trying to nail three jellies to the wall – but only having one nail. And yet with roadways having a lifetime measured in decades, that is exactly what highway engineers and traffic planners are expected to do. Fortunately, New Hampshire DoT (NHDoT) believes its technological advances may be able to provide a solution. The Central Ne