Temporary CCTV poses more challenges than permanent installations

Long-term roadworks pose particular problems for temporary surveillance installations. Converting the hard shoulder to a running lane, either full- or part-time, is the UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.
June 12, 2015 Read time: 4 mins
Frank Gearon installing feeds to the ‘Wonderbox’ for another temporary CCTV system.

Long-term roadworks pose particular problems for temporary surveillance installations.

Converting the hard shoulder to a running lane, either full- or part-time, is the 1841 UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.

Designing and implementing a number of these temporary CCTV monitoring systems for such projects is 7692 P&D Specialist Services. Current projects include 78 cameras along a 33km section of the M1 (Junctions 15-19), 109 cameras along 31km of the M3 (Junctions 2-4a) and 142 cameras on a 35km stretch of the M60 and M62 motorways around Manchester.

In April 2015 work started on a new section of ‘managed motorway’ along 23km of the M1 (Junctions 32-35a) where the hard shoulder is being converted into a running lane. As often happens with motorway projects during the construction phase the hard shoulder is inaccessible to motorists, meaning there are no emergency telephones and motorists have nowhere to stop safely and summon assistance in event of a breakdown or accident. “Before any construction work can start, temporary cameras have to be set up at regular intervals along the length of the work zone to monitor the area and detect breakdowns, accidents or incidents. That’s where the CCTV solutions we deliver come in,” says Frank Gearon, project manager of highway industry specialist P&DSS, “The aim is to deliver a real-time overview of the entire stretch of works and link all the images from the cameras back to the 24/7 manned control room.”

The company is a NICEIC contractor certified under the Highways Agency’s Sector Scheme Approval to carry out electrical works on the motorway network. At the start of this latest M1 project, it will initially deploy 30 CCTV cameras and that number will eventually double as the project progresses. Images from the cameras are streamed to a temporary monitoring station where they are also recorded, and because construction work cannot start until the cameras are working, Gearon says speed of deployment and system reliability are paramount.

“We use fibre optic cables to cope with the long distances involved, and AMG’s transmission equipment as it requires a smaller number of fibres which speeds splicing during installation. On some of the earlier projects we used AMG’s 3700 series and since 2013 we’ve used the AMG 9024– multi-service Ethernet switch (M-SES) series known as the ‘Wonderbox’.”

The ‘Wonderbox’ was designed to bridge legacy CCTV systems with new IP cameras and provides Layer 2 managed Ethernet functionality without having to involve third party products. By integrating low-speed serial data channels and alarm contacts, alongside analogue video, onto an Ethernet backbone it ‘bridges the gap’ between analogue and ‘IP’ technologies.

Due to the need to keep the roads open for traffic, such projects often run for 18 – 24 months so the CCTV systems have to withstand prolonged exposure to ambient weather conditions, vibration and dust so systems need to be very robust. 

However, that is not always enough as Gearon explains: “In major engineering projects like these, damage to cables and roadside equipment occurs frequently and there is a real risk of system failure, so on the M60/M62 project there was a requirement for a proprietary redundancy feature.

AMG was able to meet this need using the ‘X-ring’ to allow an unlimited number of M-SES units on each fibre loop, so sub-loops can be seamlessly added to provide redundancy protection in the case of a switch or fibre being damaged. And by integrating the dedicated video codec and RS232/RS485 into the MSES switch, video lag and control data is minimal.”

As the CCTV surveillance systems on the existing projects have operated over the winter period without a problem, the P&DSS/AMG solution appears to be lasting the distance.

For more information on companies in this article

Related Content

  • ITS ‘could save Australia US$500 million a year’
    February 22, 2013
    According to Australia’s federal infrastructure and transport minister, Anthony Albanese, an Australia-wide electronic freeway management system has the potential to greatly reduce congestion and save Australian families and businesses more than US$500 million a year. Albanese said as much as he announced the US$21 million contract to deliver an Intelligent Transport System (ITS) and communications infrastructure to the Westgate freeway managed motorway project in Victoria under the national smart managed m
  • Siemens SafeZone switched on in the Netherlands
    May 29, 2014
    An inter-urban version of Siemens’ SafeZone speed enforcement system has been deployed and switched on in the Netherlands this month to discourage motorists from exceeding 80 kph on two sections of the A13 motorway, the main arterial route between Rotterdam and The Hague. Modified for the Dutch market, the award-winning solution was designed, supplied and installed by Siemens for the Ministry of Justice, Netherlands and will be serviced for a period of eight years. Based on automatic number plate re
  • Nairobi looks to ITS to ease travel problems
    December 21, 2017
    Shem Oirere looks at plans to tackle chronic congestion in the Kenyan capital. Traffic jams in the Kenyan capital, Nairobi, are estimated to cost the country $360 million a year in terms of lost man-hours, fuel and pollution. According to Wilfred Oginga, an engineer with the Kenya Urban Roads Authority (KURA), the congestion has been exacerbated by poor regulation and enforcement of traffic rules, absence of adequate traffic management systems and poor utilisation of existing road facilities.
  • New series of Sony block cameras
    February 2, 2012
    Sony's latest FCB E-Series of colour block cameras, which cover a variety of features, optical zoom ranges and advanced capabilities including progressive scan imaging, is designed to provide original equipment manufacturers and systems integrators with the right camera for an expanding number of applications including security, intelligent traffic, unmanned vehicles, low vision, inspection and videoconferencing.