Temporary CCTV poses more challenges than permanent installations

Long-term roadworks pose particular problems for temporary surveillance installations. Converting the hard shoulder to a running lane, either full- or part-time, is the UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.
June 12, 2015 Read time: 4 mins
Frank Gearon installing feeds to the ‘Wonderbox’ for another temporary CCTV system.

Long-term roadworks pose particular problems for temporary surveillance installations.

Converting the hard shoulder to a running lane, either full- or part-time, is the 1841 UK Highways Agency’s solution to ease motorway congestion. This is leading to a number of long-term projects where large stretches of the hard shoulder are closed off by temporary concrete barriers and during these roadwork programmes, temporary CCTV cameras are deployed to monitor and record vehicle traffic and workers.

Designing and implementing a number of these temporary CCTV monitoring systems for such projects is 7692 P&D Specialist Services. Current projects include 78 cameras along a 33km section of the M1 (Junctions 15-19), 109 cameras along 31km of the M3 (Junctions 2-4a) and 142 cameras on a 35km stretch of the M60 and M62 motorways around Manchester.

In April 2015 work started on a new section of ‘managed motorway’ along 23km of the M1 (Junctions 32-35a) where the hard shoulder is being converted into a running lane. As often happens with motorway projects during the construction phase the hard shoulder is inaccessible to motorists, meaning there are no emergency telephones and motorists have nowhere to stop safely and summon assistance in event of a breakdown or accident. “Before any construction work can start, temporary cameras have to be set up at regular intervals along the length of the work zone to monitor the area and detect breakdowns, accidents or incidents. That’s where the CCTV solutions we deliver come in,” says Frank Gearon, project manager of highway industry specialist P&DSS, “The aim is to deliver a real-time overview of the entire stretch of works and link all the images from the cameras back to the 24/7 manned control room.”

The company is a NICEIC contractor certified under the Highways Agency’s Sector Scheme Approval to carry out electrical works on the motorway network. At the start of this latest M1 project, it will initially deploy 30 CCTV cameras and that number will eventually double as the project progresses. Images from the cameras are streamed to a temporary monitoring station where they are also recorded, and because construction work cannot start until the cameras are working, Gearon says speed of deployment and system reliability are paramount.

“We use fibre optic cables to cope with the long distances involved, and AMG’s transmission equipment as it requires a smaller number of fibres which speeds splicing during installation. On some of the earlier projects we used AMG’s 3700 series and since 2013 we’ve used the AMG 9024– multi-service Ethernet switch (M-SES) series known as the ‘Wonderbox’.”

The ‘Wonderbox’ was designed to bridge legacy CCTV systems with new IP cameras and provides Layer 2 managed Ethernet functionality without having to involve third party products. By integrating low-speed serial data channels and alarm contacts, alongside analogue video, onto an Ethernet backbone it ‘bridges the gap’ between analogue and ‘IP’ technologies.

Due to the need to keep the roads open for traffic, such projects often run for 18 – 24 months so the CCTV systems have to withstand prolonged exposure to ambient weather conditions, vibration and dust so systems need to be very robust. 

However, that is not always enough as Gearon explains: “In major engineering projects like these, damage to cables and roadside equipment occurs frequently and there is a real risk of system failure, so on the M60/M62 project there was a requirement for a proprietary redundancy feature.

AMG was able to meet this need using the ‘X-ring’ to allow an unlimited number of M-SES units on each fibre loop, so sub-loops can be seamlessly added to provide redundancy protection in the case of a switch or fibre being damaged. And by integrating the dedicated video codec and RS232/RS485 into the MSES switch, video lag and control data is minimal.”

As the CCTV surveillance systems on the existing projects have operated over the winter period without a problem, the P&DSS/AMG solution appears to be lasting the distance.

Related Content

  • February 2, 2016
    Smarter motorway for West Yorkshire
    Drivers on the M1 near Wakefield will benefit from reduced congestion and improved journey times after the final phase of a new US$172 million smart motorway went live. The Highways England scheme along a seven-mile stretch of motorway between junction 39 and junction 42 is the first all lane running motorway in the north, where the hard shoulder has been permanently converted to an extra lane. The smart motorway uses the latest technology to monitor traffic levels and variable speed limits on overhea
  • June 19, 2014
    Manchester orbital route to become ‘smart motorway’
    Four companies, Balfour Beatty, together with Costain, Carillion and a BAM Nuttall Morgan Sindall joint venture, have been awarded the contract to upgrade a 17 mile stretch of the M60 and M62 to a ‘smart motorway’. The US$313 million upgrade, for the UK Highways Agency, aims to increase capacity, reduce congestion and shorten journey times for motorists. The M60 between junctions 8 and 12 will be upgraded to a controlled motorway with traffic flows managed by technology interventions responsive to the
  • February 12, 2013
    M62 managed motorway scheme signs switched on
    Work to upgrade part of the M62 in West Yorkshire to a managed motorway, the first scheme in the Yorkshire and Humber region, reached a significant milestone when the first overhead electronic signs went live. For the first time, the variable advisory speed limit signs have come into operation between junctions 27 and 28 to allow the UK Highways Agency to calibrate and test the technology required for the new managed motorway, with the signs being switched on and off in response to traffic conditions. Advis
  • December 9, 2016
    Four drivers a month deliberately ignore Manchester motorway closures
    Highways England is urging drivers Highways England is not to put road workers’ lives at risk by deliberately ignoring road closures on the M60 and M62 near Manchester. New figures have revealed that four drivers a month are entering closed sections of road in the Manchester smart motorway scheme to either overtake traffic on the motorway or avoid using diversion routes. Highways England has released CCTV footage showing a driver ignoring an overnight slip road closure at junction 11 of the M60 at Ecc