Upgrade for Humber Bridge toll system

Work has begun on an ambitious US$8 million project to implement an innovative new electronic tolling system at the UK’s Humber Bridge, where the existing systems have remained largely unchanged since the bridge opened in 1981. The project is set to be completed by autumn/winter 2014 and will include a major redevelopment of the tolling plaza and systems, together with the creation of some of the first open tolling free-flow lanes in the UK. These will enable drivers to cross the Humber Bridge without s
August 20, 2013 Read time: 2 mins
Work has begun on an ambitious US$8 million project to implement an innovative new electronic tolling system at the UK’s Humber Bridge, where the existing systems have remained largely unchanged since the bridge opened in 1981.

The project is set to be completed by autumn/winter 2014 and will include a major redevelopment of the tolling plaza and systems, together with the creation of some of the first open tolling free-flow lanes in the UK.  These will enable drivers to cross the Humber Bridge without stopping and are designed to reduce crossing times and congestion at busy times.

The number of traditional cash tolling booths reduced from six in each direction to three. These will also be redesigned to feature automatic barriers, in an effort to streamline the tolling and crossing process.

Customers opting to use electronic tolling will attach a small tag to their vehicle windscreen, which will be automatically read each time they cross the bridge. These tags will be tied to a customer account, which will then be debited each time they cross the bridge.

Benefits of the scheme include uninterrupted crossing, leading to faster journey times, a way to avoid fumbling for loose change or pre-paid tickets at the toll plaza, improved convenience and a user-friendly toll account.

Peter Hill, general manager and bridgemaster of the Humber Bridge, sees the project as a very positive step, as he explains: “The toll collection system currently in operation at the Humber Bridge has remained largely unchanged for the past thirty years, and still uses a fifteen year-old computer system, along with obsolete equipment and programming technology which requires an increasing amount of maintenance.

“When faced with the unavoidable need to replace the system, we made it our aim to provide bridge users with the most convenient crossing experience possible and opted to bring in a new scheme which will offer a modern, innovative and sustainable solution for the future.”

Related Content

  • Humber Bridge toll goes ORT
    October 17, 2014
    Civil engineering firm Britcon has completed works for a new US$8.8 million state-of-the-art toll collection facility on the Humber Bridge to replace the toll collection system which was installed in 1981. The new collection system will include one of the first open road tolling arrangement to be installed in the UK, where vehicles do not need to stop while driving through the toll plaza. Britcon undertook full infrastructure works for the project on behalf of Sociedad Ibérica de Construcciones Eléctrica
  • Countdown to Humber Bridge open-road tolling
    July 22, 2015
    From early November 2015, the multi-million pound Humber Bridge project will introduce the UK's first electronic toll collection (ETC) and open-road tolling system to the bridge, enabling motorists who apply for a HumberTag account to pay the toll automatically using an electronic tag linked to a personal online account. The middle lanes of the bridge won’t have any booths and will be for account holders only – enabling drivers to cross the bridge without stopping. The outside lanes will still have booth
  • Free-flow upgrade to Holland's Westerschelde tunnel's toll system
    February 1, 2012
    Unbroken service Technolution's Winifred Roggekamp and Dave Marples describe efforts to upgrade the Westerscheldetunnel's tolling system to give free-flow capability. Until 2003 the Flanders region of Zeeland, in the south-west of the Netherlands, was connected to the mainland only by ferry. The new Westerscheldetunnel, a 6.6km toll tunnel, improves communications with the region considerably, taking some 100km off the alternative road journey. In 2006 it was recognised that the toll plaza for the tunnel ne
  • Mersey Gateway tolling system launched
    March 1, 2017
    Tolling arrangements for the new Mersey Gateway in the UK have been announced. Both the new bridge and the Silver Jubilee Bridge will be tolled from autumn 2017. The Mersey Gateway is a new road bridge across the River Mersey and the Manchester Ship Canal in north-west England, which began construction in May 2014.