A new ten year plan released by the Maine Turnpike Authority defers decisions on work to upgrade its three largest toll plazas pending completion of a next generation toll collection study that will consider the costs and benefits of going all-electronic, versus open road electronic tolling (ORT) and cash and a timetable. Objections from local residents and the failure of the Turnpike to consider the alternative of all-electronic tolling (AET) led to the delay of a previous ten year plan in 2009 that set
December 19, 2013 Read time: 2 mins
A new ten year plan released by the Maine Turnpike Authority defers decisions on work to upgrade its three largest toll plazas pending completion of a next generation toll collection study that will consider the costs and benefits of going all-electronic, versus open road electronic tolling (ORT) and cash and a timetable.

Objections from local residents and the failure of the Turnpike to consider the alternative of all-electronic tolling (AET) led to the delay of a previous ten year plan in 2009 that set 2011 as the year for start on rebuild of the main south-end toll plaza designed to be an ORT plus cash plaza.  

April this year saw the beginning of ORT in some areas of the toll road and other ORT conversions of central lanes are planned, keeping some cash collection to each side. The cash toll collection system meanwhile is being replaced.

Cash continues to be the payment mode for some 37 per cent of transactions, and similar for Maine E-ZPass. The major growth in electronic tolling has come from travellers from outside with non-Maine E-ZPass transponders, now generating 25 per cent of transactions.

The new US$258m million ten year capital plan has US$123 million budgeted for bridge rehabilitation, US$70 million for pavement rehabilitation, $21 million for interchange improvements and US$19 million for immediate toll system upgrades.

Related Content

  • January 30, 2012
    Open road tolling: safer with less congestion
    Michael J. Davis of PBS&J looks at the positive effect that open road tolling can have on safety
  • August 20, 2013
    Massachusetts moves ahead on AET
    The Massachusetts Department of Transportation (MassDOT) has scheduled three public meetings to present all electronic tolling (AET) information and solicit comments from members of the public. MassDOT proposes to convert and replace the I-90 Western Turnpike and I-90 Boston Metropolitan Highway System interchange-based manual cash and electronic toll collection systems with a new system of tolling relying only on AET. The project will include both roadway tolling infrastructure and toll collection sys
  • February 21, 2013
    New York State Thruway to go all electronic
    The New York State Thruway is converting two mainline and one side toll plaza to all electronic (AET) or cashless toll collection, in a drive to contain spiralling employee costs and debts caused by a reduction in traffic. Although the original plan called for open road tolling (ORT) plus a cash toll plaza, the Request for Proposals for the new bridge allowed bidders to propose AET during the construction if that reduced disruption of traffic. Work is now starting on the new bridge which under the contract
  • December 23, 2021
    Covid turns tolls cashless
    When coronavirus hit, Pennsylvania Turnpike Commission made its long-planned e-tolling system permanent; this made sense, but it was still a difficult decision, explains the organisation’s Carl DeFebo