Funding agreed for reconstruction of Fort Worth I-35W

A significant milestone in the redevelopment and expansion of Interstate 35W in Fort Worth, one of the most critical and most-congested corridors in the North Texas region and in the country has been achieved by NTE Mobility Partners Segments 3 LLC (NTEMP3). They have reached financial agreement on Segment 3A of the North Tarrant Express (NTE), paving the way for the reconstruction and expansion of the interstate. The project is being financed through a unique combination of public and private funds: US$
September 20, 2013 Read time: 3 mins
A significant milestone in the redevelopment and expansion of Interstate 35W in Fort Worth, one of the most critical and most-congested corridors in the North Texas region and in the country has been achieved by NTE Mobility Partners Segments 3 LLC (NTEMP3). They have reached financial agreement on Segment 3A of the North Tarrant Express (NTE), paving the way for the reconstruction and expansion of the interstate.

The project is being financed through a unique combination of public and private funds: US$531 million from a federal Transportation Infrastructure Finance and Innovation Act (TIFIA) loan; US$430 million in private equity from investment partners; $274 million in Private Activity Bonds (PABs) maturing in 25 and 30 years; and US$127 million in public funds from TxDOT and NCTCOG.

“This is a huge win for Texas, and demonstrates significant market confidence in this public-private partnership,” said Nicolas Rubio, president, 5428 Cintra US. “Through this innovative public-private partnership, TxDOT and the North Central Texas Council of Governments (NCTCOG) have utilised the strength of the private sector to deliver this project years sooner than otherwise possible and at vastly reduced public costs, while creating local job growth and fostering economic development for the region.”

“The I-35W project has been on the drawing board for decades, but could not advance due to a lack of funding,” said Richard Tettamant of the Dallas Police and Fire Pension System. “Today’s announcement means that North Texas families, commuters and employers will soon have much-needed and long-anticipated relief. We are proud to be investing in the future growth of the Metroplex.”

NTEMP3 will undertake the construction of the US$1.4 billion project to rebuild 6.5 miles of the existing main lanes of I-35W, construct new, expanded frontage roads and expand the highway with the addition of two TEXpress managed toll lanes in both directions, doubling the capacity of the highway.  Construction is expected to begin this fall, with substantial completion in 2018. Segment 3B is being constructed by the 375 Texas Department of Transportation (TxDOT) and will be operated by NTEMP3.

The TEXpress managed toll lanes, which will be implemented in Texas for the first time with the opening of the initial segment of the LBJ Express, will help to manage traffic flow by adjusting according to traffic speed and traffic volume.

“TEXpress Lanes will significantly enhance traffic flow in the region, especially for longer-trip commuters,” said Belen Marcos, CEO for NTEMP3

NTEMP3 is led by Cintra US, a world leader in the private-sector development of transportation infrastructure, and Meridiam Infrastructure, who has extensive expertise in global public-private partnerships as an investor/developer of public facilities. The equity members also include the Dallas Police and Fire Pension System and APG.

Related Content

  • May 3, 2012
    Texas highway loan stars revealed
    A loan of US$415million from the US government’s Transportation Infrastructure Finance and Innovation Act programme will help meet the cost of building toll lanes and rebuilding existing lanes at the Interstate 35 highway (I-35W) near Fort Worth, Texas. The works are part of the $2.5billion North Tarrant Express project, which is currently under construction in the northeastern part of Tarrant County, Texas. A consortium of companies led by Spanish toll road developer Cintra, NTE Mobility Partners is behi
  • February 18, 2014
    Kapsch TrafficCom awarded Texas tollway extension project
    Kapsch TrafficCom has been selected by North Tarrant Express (NTE) Mobility Partners Segments 3 LLC to provide the toll collection, intelligent transportation and network communication systems for the NTE extension project. The NTE extension is approximately ten miles long, and runs along I-35W north of the city of Fort Worth. Kapsch will deliver ten all-electronic toll zones, including dynamic sign equipment and road sensors that provide the data to enable dynamic toll charges based upon actual traffic
  • July 31, 2012
    Kapsch wins Texas tolling projects
    Kapsch TrafficCom IVHS, a subsidiary of Kapsch TrafficCom, has been selected to design, build, and integrate the managed lane system (MLS) for both the North Tarrant Express (NTE) and LBJ Express projects in Dallas and Tarrant Counties in North Texas.