By David Arminas November 16, 2020 Read time: 2 mins
Artist’s impression of the Lower Thames Crossing’s northern tunnel entrance in the county of Essex, looking south (image: Highways England)

Highways England’s planned £2 billion Lower Thames Crossing will have a free-flow charging system, similar to that of the nearby Dartford Crossing.

Highways England has just tendered for what will be the government-owned agency’s largest-ever contract that will include Britain’s longest road tunnel, a 4.2km-long twin tunnel under the River Thames, east of London.

There will also be traffic regulation measures that include prohibiting use by pedestrians, low-powered motorcycles, cyclists, horse riders and agricultural vehicles.

The existing Dartford Crossing, which was designed for 135,000 vehicles a day, often sees 180,000 a day. It also can take three to five hours for the roads to clear following a closure.

In its first year, more than 27 million drivers are forecast to use the Lower Thames Crossing, providing much-needed relief at Dartford.

The Crossing will improve journeys by almost doubling road capacity across the Thames River, thanks to 23km of new road of three lanes in both directions. 

Work could start in early 2022, according to Highways England, which is responsible for modernising, maintaining and operating England’s motorways and major A roads. 

At 16m wide, the tunnels - one for southbound traffic, the other for northbound traffic - will be some of the largest bored tunnels in the world, says the agency. The scope also includes portal buildings, approach roads and the tunnel systems.

The agency said that it expects that three applicants will be shortlisted to move forward into a competitive dialogue stage.

The tunnels and approaches contract is the first of the three main works contacts for the scheme. Following this deal will be the Roads North and the A2/M2 contracts which are expected to be announced early next year.

“The Lower Thames Crossing is the most ambitious road project this country has seen since the M25 was completed nearly 35 years ago,” said Matt Palmer, executive director of Lower Thames Crossing. 

“The scheme will relieve congestion at the Dartford Crossing by providing a new free-flowing road, almost doubling road capacity across the Thames and supporting sustainable local and regional economic growth.”
 
Keith Bowers, tunnels and systems director for the Lower Thames Crossing, added: “We have committed to targets that mean by 2040 nobody will be killed or seriously injured on our roads and motorways and we need our contractors’ design and delivery to meet that target for our road users and workers.”
 

For more information on companies in this article

Related Content

  • Stepped speed limits improve workzone congestion and safety
    January 30, 2012
    Traffic flow has been improved, congestion eased and safety increased - by a system of 'stepped speed limits' introduced to UK roadworks. URS Scott Wilson principal consultant Jamie Uff reports
  • Electrosonic installs Hindhead tunnel control room display
    December 3, 2012
    The twin-bore Hindhead tunnel in southern England has made the A3 London to Portsmouth route safer and more efficient, aided by the large overview video wall and operator consoles installed in the control room by Electrosonic, working with main contractor Balfour Beatty Engineering Services for the Highways Agency. To meet the Highways Agency’s requirement that the control room should operate in a similar way to other traffic control rooms on the major road network, Electrosonic devised a solution based on
  • Autonomous driving – what can we really expect?
    June 6, 2016
    Dave Marples of Technolution BV looks beyond the hype to the practical implementation of autonomous vehicles. Having looked at the development of this sector for some time, I am concerned about the current state of autonomous driving development as engineering (and marketing) have run way ahead of the wider systemic, and legislative, requirements to support an autonomous future.
  • Road user charging potential solution to transportation problems
    December 14, 2012
    A number of new and highly significant open road tolling schemes have just been launched or are soon to ‘go live’. Systems of road user charging are flexing their muscles as the means to solve politically sensitive transportation problems, reports Jon Masters. Gothenburg, January 2013, will be the time and place for the launch of the next city congestion charging scheme in Europe. In a separate development, Los Angeles County’s tolled Metro ExpressLanes began operating in November 2012 – the latest in a ser