Two phases of an arterial reconstruction project in Salt Lake City have provided a compelling cost-based argument for moveable barriers.
January 25, 2012 Read time: 4 mins
Two phases of an arterial reconstruction project in Salt Lake City have provided a compelling cost-based argument for moveable barriers.

Construction has recently been completed on 3500 South in Salt Lake City, Utah, which was completely reconstructed by UDOT Region 2 from the Bangerter Highway to 2700 West to build Utah's first Bus Rapid Transit lanes. With a significant ADT that runs between 38,000 and 48,000 vehicles throughout the corridor, keeping traffic moving was the most important and the most difficult task during construction.

The first phase of the project called for two lanes to be open for traffic in each direction, and plastic barrels were used to separate directional traffic and to delineate the work zone. The work zone area was confined and restricted, and it lacked positive protection which created dangerous conditions as confused motorists occasionally turned into the work zone. In addition, accidents occurred when drivers made left turns into businesses through the barrels, which contributed to congestion. The contractor needed a larger, more protected work space, and the traffic management plan needed a way to limit the number of left-hand turn options for motorists without restricting traffic flow.

Phase II

For the second phase of the project, after reviewing several options, UDOT elected to employ a reversible lane using moveable barrier technology from 21 Barrier Systems International. The moveable barrier could keep two lanes open to traffic in the peak direction by using a total of only three lanes, instead of the four lanes required when using barrels. This would give the contractor an extra lane to expand the work zone, keeping workers safe and accelerating construction without causing additional traffic congestion.

Project:
• Use of moveable barrier on arterial reconstruction, Salt Lake City

Benefits:

• US$2.4 million in quantified benefits (4:1 B/C ratio)
• B/C ratio of greater than 10:1 with all benefits considered
• US$1million in accident savings
• Project accelerated by seven months
• User delay savings from early completion
• Savings from reduced accidents
• Lower impact to businesses on the corridor
• Contractor TRO saving
The barrier would also limit left-hand turns to five major intersections. 2.7 km of moveable barrier was deployed as a positive barrier separation between east and westbound traffic, and the barrier was moved multiple times daily to create a 1/2, 2/1 traffic pattern based on peak traffic needs. The barrier was transferred 3.7m, or one lane width, in one pass at 8km/h (5mph). The entire transfer took approximately 20 minutes, including repositioning the traffic control and signage.

With the expanded work zone, the contractor was able to use larger, more efficient equipment and work unimpeded for longer periods of time while the barrier was in place. This resulted in the elimination of one complete phase of construction, reducing the total number of phases from three to two. The accelerated construction schedule helped the contractor to finish the project seven months early. In a report commissioned by UDOT and compiled by T.Y. Lin International, the user delay savings from the early completion were estimated at US$1.3 to $1.4 million (vehicle operating costs were not included). The businesses on the corridor also benefited from the early project completion, which ended the disruption to business from the construction work zone. While the UDOT report did not quantify these benefits, it did consider them to be "significant"

Positive protection

The barrier limited left-hand turns except at five major intersections, which reduced accidents and helped keep traffic running smoothly. The report estimates that, based on the average number of left-hand turns in the corridor, the
barrier eliminated 20 to 25 left-turn crashes while in operation, with an estimated reduction in crash costs of an additional $1 million Safety was also enhanced for construction workers and motorists with the moveable concrete barrier. The positive protection provided by the barrier eliminated work zone encroachments.

The benefits that were determined from the use of moveable barrier included reduced user costs, shorter travel distances, improved safety, lower impacts to businesses, early project completion, less fuel use and reduced air emissions. The report conservatively estimated the total benefits of using moveable barrier on the project at between US$1.7 to $2.4 million, with a benefit/cost of 4:1 (considering user delay costs and accident savings only). The authors also stated that if all benefits were considered (such as the reduced air emissions and benefits of early completion for businesses), the benefit/cost ratio for the moveable barrier system would be greater than 10:1.

For more information on companies in this article

Related Content

  • Section speed enforcements gains global converts
    October 26, 2017
    As the benefits of section speed enforcement are becoming clearer, the technology is gaining converts worldwide. Colin Sowman reports. America’s National Transportation Safety Board (NTSB) is calling for urgent action from both road authorities and the federal government to combat speeding which has been identified as one of the most common factors in motor vehicle crashes in the United States. This new call follows the publication of a safety study which found that between 2005 through 2014, 31% of all
  • Troopers in the TOC – a recipe for success
    May 11, 2016
    A traffic incident management project in Arizona has speeded up reopening closed lanes and saved an estimated $165m through reducing traffic delays. The process for clearing roadway incidents on the Maricopa County freeways in Arizona has always reflected industry best practice with, for instance, a live feed of freeway cameras to the Arizona Department of Public Safety’s (DPS) dispatch centre and the City of Phoenix Fire dispatch centre. The region has nearly 480km (300 miles) of freeway connecting 27 citi
  • IBTTA summit hits right notes in Salzburg
    December 5, 2018
    In the birthplace of Mozart, Colin Sowman found that delegates at the IBTTA’s inaugural World Tolling Summit were playing a variety of interesting tunes The first World Tolling Summit took place in Salzburg, Austria this autumn. Created and organised by the International Bridge Tolling and Turnpike Association (IBTTA), the event was supported by its European counterpart Asecap and hosted by Austria’s tolling authority, Asfinag. The transfer of views, experience and practice both ways across the Atl
  • Smart Spanish city trials cell-based traffic management
    November 7, 2013
    David Crawford reports on an urban electronic nervous system. The northern Spanish city of Santander – historically a port - is now an emerging technology showcase attracting global attention as a prototype for a medium-sized smart city of the future. In a move to determine the optimal use of available data, it is creating a de-facto experimental laboratory for sensor and mobile phone-based urban traffic management and environmental monitoring innovations.