A combination of technologies is leading to major congestion and cost reductions during roadworks on the UK’s motorway network. Innovative construction programme scheduling technology and the deployment of moveable barriers has achieved substantial savings of money and time on UK motorway roadworks managed by the Highways Agency (HA). This combination has set the scene for a new generation of road usage analysis tools. The HA’s objective was to reduce the congestion caused by lane closures during roa
March 17, 2014 Read time: 7 mins
Barrier Systems’ QMB moveable barrier system was used to open and close lanes in response to DRUM’s predictions.
A combination of technologies is leading to major congestion and cost reductions during roadworks on the UK’s motorway network.

Innovative construction programme scheduling technology and the deployment of moveable barriers has achieved substantial savings of money and time on UK motorway roadworks managed by the 503 Highways Agency (HA). This combination has set the scene for a new generation of road usage analysis tools.

The HA’s objective was to reduce the congestion caused by lane closures during roadworks, while also enabling the work to finish as quickly as possible. To do this the technology is providing greater accuracy in the prediction of traffic flows and in matching current demand to capacity in a range of scenarios.

Named DRUM (Dynamic Roadspace Utilisation Manager), the traffic management system models a number of custom traffic layout options within the roadworks. It operates by collecting live traffic flow information from web-connected portable radar sensors and comparing that data with historic traffic flows. The system then assesses the optimum times for lane closures, predicting times when lanes should be opened and closed depending on traffic demand, thereby helping to ensure reliable journey times through the roadwork section.

This new approach replaces the conventional use of rigid lane closure timetables in favour of flexible working windows that are derived from historical profiles and responds to actual traffic flows. In doing so it allows lane closures to begin earlier and finish later, with work continuing whenever conditions allow and providing useful opportunities to progress the scheme faster. As DRUM produces information about when traffic flows will increase and require running lanes to be reopened for traffic, the system helps reduce the likelihood of congestion.

Contract value
US$6.6 million

Predicted saving
US$99,825

Actual saving
US$412,500
Originally the technical challenge was to create a reliable traffic model using real-time traffic flows for a scheme on the southern approaches to the Dartford Crossing over the River Thames on London’s orbital motorway, the M25. The system needed to provide easily accessible information covering junctions 3 to 1B which allowed the contractor to open and close running lanes using the moveable barrier system as demand changed in order to prevent unnecessary congestion. 
The desired result was to speed up the construction programme by benefitting from extended working hours by restricting lane closures to periods when the full capacity was needed and resulted in transport consultancy 491 TRL and construction contractor 2002 Costain developing DRUM. The original version used Moorway Incident Detection and Automated Signalling (MIDAS) traffic monitoring system loop data from outside the works area (see panel). This fed into a web service, hosted at TRL, to provide live traffic counts that could be used to present timetables for potential lane closures.

This pilot scheme also used the Quickchange Moveable Barrier (QMB) system, supplied by traffic barrier specialist Highway Care, to speed up lane opening and closing. It deploys a linked chain of concrete sections that can be ‘zipped’ across a carriageway by a self-propelled barrier transfer machine, which quickly creates a safe working area without needing a wide buffer zone and the resulting traffic impacts.

Since the pilot, DRUM has expanded to incorporate additional information inputs and outputs. By working with radar sensor equipment providers MTS UK the DRUM  system is now configured to be useable without pre-existing traffic data.

Where there is no historic data, early deployment of sensors enable the collection of relevant data prior to the commencement of the construction. Contractors can view planning, operations and assessment tools using a bespoke web service, developed to be accessible via any internet-enabled device.  

The planning tool shows two weeks’ worth of predicted timetables which are updated as live data is processed, to allow contractors to adjust schedules ahead of time. A traffic light icon in the operations tool indicates if and when a lane can be opened or closed and is the live system most use from the roadside to support existing information and safety checks. Within the assessment tool is a queuing model that allows users to forecast sets of lane closures and study predicted effects on queuing.
The whole system can be used globally on any trunk road where there is mobile data availability.

DRUM has been used on six schemes to date, including the pilot. Over the initial two-year programme on the M25, it helped the contractor’s team deliver more than 20 additional working hours a week.  This resulted in the construction period being cut by six months and a saving of £1,171,500 (US$1,933,000). More recently DRUM has been deployed on the M61 in North West England. Before the scheme began, the team predicted a conservative net saving of £60,500 (US$99,825) based on shortening the programme by two weeks.

In the end, the £4.1 million (US$6.6 million) scheme gained an additional 135 working hours, finished four weeks ahead of schedule and saved £250,000 (US$412,500). Other benefits of allowing the traffic management to be installed on the network earlier and removed later included:

• Elimination of queuing during the construction programme, including periods when lane closures were in place outside conventional roadwork operating hours. In addition, there were no complaints from members of the public about the traffic management.

• The use of daytime working at weekends allowed noisier activities to be completed during the day, resulting in fewer noise complaints from the public.

Additionally, the radar sensors, provided by MTS UK, did not require recalibrating during the scheme as top-up charging from solar panels enabled the batteries to last for the full duration of the works without recharging.   

As DRUM records all received data for audit purposes, the M61 scheme also provided speed information to prove that the safety cameras being used were effective in lowering motorists’ speeds through the work zone.

MIDAS

MIDAS is a distributed network of traffic sensors designed to alert control centres to traffic flow and average speeds and, in active traffic management zones, set variable message signs and advisory or mandatory variable speed limits, with minimal human intervention. Traffic information providers such as 1692 TomTom and 1691 Google access this data using the HA National Traffic Operations Centre’s DATEX II set of European specifications. 
TRL believe that DRUM’s biggest benefits will be identifying locations where traffic flows are low enough to justify lane closures across the weekend and the overnight working window can be extended. However, the benefits reduce as two or more lanes need closing, because traffic flows need to be lower to reduce the chance of queuing on the remaining running lanes.

Looking ahead

TRL is currently looking to expand DRUM’s potential and has developed system tools for contractors including a smartphone application which can send SMS message alerts at designated times to the staff on site giving notice that the lane is about to be opened or closed.

Another potential variation is the use of alternative sources such as satellite-derived data. This could be useful on dual carriageways, allowing contractors to monitor congestion in the surrounding area on local roads. TRL is also conducting new research into traffic patterns using modelling and microsimulation tools and is continuing its partnership with Costain.

Cooperative driving – challenges ahead

Following initiatives including the publication of the European i-Mobility Forum’s road map, the International Benefits, Evaluation and Costs Working Group is keeping a watchful eye on developments in cooperative and automated driving. ITS practitioners belonging to 1874 The Working Group warn that, without first mastering the full potential of V2X (networked vehicle) technology, the disbenefits of cooperative and automated driving could outweigh the benefits.

The organisation is also concerned about how to estimate the benefits of cooperative and automated driving. Greater driving comfort and convenience are the most directly achievable benefits but these are hard to quantify in practice. While traffic flow smoothness, increased road capacity, reduced emissions and other environmental benefits can only be maximised with full V2X cooperative automation, there are indications this could mitigate traffic shockwaves.

Safety benefits will be the hardest to achieve, quantify and cost as there is not an existing credible approach and there also remains the issue of where to place the blame for accidents – on drivers or equipment suppliers.

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal sites.Google.com/site/ibecits https://sites.google.com/site/ibecits/ false https://sites.google.com/site/ibecits/ false false%>




















Related Content

  • October 6, 2015
    Lindsay focuses on safety with Road Zipper barrier
    You can’t miss Lindsay Transportation Solutions’ here at the ITS World Congress: the company’s Road Zipper System creates a flexible, positive traffic barrier between opposing lanes of traffic or between motorists and construction work zones while managing congestion.
  • January 25, 2012
    US state of the art workzone safety
    The Texas Transportation Institute's Jerry Ullman talks about the state of the art in work zone safety in the US. Work zones are places where, perhaps more than anywhere else on the road network, mobility and safety are strongly linked. Historically, field crews and contractors wanted vehicles in work zones to be moving as slowly as possible, assuming that made conditions the safest for work crews. We are though starting to see a shift in such thinking with the realisation that excessive delays or slow-down
  • July 17, 2012
    Development of cooperative driving applications for work zones
    The German AKTIV project is researching several cooperative driving applications for use in work zones. PTV's Michael Ortgiese details progress. The steep increases in traffic volumes predicted back in the early 1990s have unfortunately been proven to be more than accurate. In Germany, the AKTIV project continues to look into cooperative technologies' potential to reduce the impact of those increased traffic volumes and keep traffic moving despite limitations in infrastructure capacity.
  • July 23, 2012
    Radar effective as detection tool for hard shoulder running
    Navtech Radar's millimetric-wave systems are being researched on the M42 in England to look into how this type of detector can assist in the opening of the hard shoulder as an additional running lane. Here, the company's Stephen Clark talks about the technology being used. In England, the Highways Agency's (the HA, an executive agency of the Department for Transport) Managed Motorways system - formerly called Active Traffic Management - uses electronic signs and signals mounted on gantries to direct drivers