Croix-Rousse demonstrates art of tunnel safety

How do you expand a tunnel when it has reached its traffic limit? Build another tunnel in parallel to it. That, at least, is what Lyon did and opened the 1.7km Croix-Rousse dual-tunnel system in 2013. The smaller, new €283 million tunnel has become a symbol of Lyon’s intention to reinvent itself as one of France’s most innovative mobility centres, said Mathieu Hermen, head of operations at La Metropole de Lyon. Construction of the original two-lane tunnel under one of the city’s most densely populated arro
December 6, 2018 Read time: 3 mins
Eco-tunnel: the Croix-Rousse in Lyon
How do you expand a tunnel when it has reached its traffic limit? Build another tunnel in parallel to it. That, at least, is what Lyon did and opened the 1.7km Croix-Rousse dual-tunnel system in 2013. The smaller, new €283 million tunnel has become a symbol of Lyon’s intention to reinvent itself as one of France’s most innovative mobility centres, said Mathieu Hermen, head of operations at La Metropole de Lyon.


Construction of the original two-lane tunnel under one of the city’s most densely populated arrondissements started in 1939. Work was halted by the Second World War when the site was used as an air-raid shelter. It was finally opened in 1952. The original tunnel has a speed limit of 50kph and nearly 50,000 vehicles use it daily.

Physical separation


A concrete barrier was installed in 1998 to physically separate the two lanes, both of which have a useable width of almost 6m. But physical deterioration by then was starting to be a concern, as well as a lack of escape tunnels, which meant something had to be done.

Much consultation ensued to consider options such as double-decking the original tunnel and widening it. But the chosen option was to make a parallel tunnel and use it for more eco-friendly modes of mobility.

The single vehicle lane is for public transportation – buses – and there is a separate two-way cycle path as well as a wide separate pedestrian path. Thanks to 11 cross-galleries the latest 10m-wide tunnel acts as the escape tunnel for the original vehicle tunnel, explained Hermen. Around 2,300 cyclists and 2,000 pedestrians use the new tunnel each day.

The busway – a one-way direction - can be later adapted for use by a tramway should the city decide to go down that route. Only one bus at a time is allowed through the tunnel in case of a breakdown that could snarl up other buses behind the stricken vehicle.

Emergency escape


A barrier, almost 1m high, separates the busway from the cycle lane. But there are many sections of the barrier that will slide open in the case of an emergency, should people need to escape the tunnel. The escape cross-galleries are sealed by heavy doors that are motorised for ease of opening from inside. There are also digital temperature readouts inside the galleries so occupants know, in the case of a fire, what the temperature is right behind the door. A main control centre for all motorways and the tunnels in Lyon lies some way away, but there is a small operations control centre at one end of the new Croix-Rousse for monitoring an emergency situation on-site.

During a technical tour of the Croix-Rousse ‘eco-tunnel’, delegates experienced the three-dimensional video show that covers much of the infrastructure’s walls. The artistry and imagination has turned a city commuter’s daily experience into a must-visit for many tourists to Lyon.

Related Content

  • Hot spot detector prevents road tunnel fires
    December 9, 2013
    Sick’s new hot spot detector system proved its worth only one week after being installed by preventing a fire in the Karawanks Tunnel, Austria. A semi-trailer truck with a wheel temperature exceeding 200 degrees centigrade triggered the alarm as it passed the hot spot detector. Closer inspection indicated that in addition to the overheated brake, the vehicle was also travelling with two cracked brake discs. Developed by Sick’s Swiss subsidiary ECTN and based on the Sick LMS511 laser sensor with the T
  • Dura-Line lays fibre along Ohio’s Smart Mobility Corridor
    June 7, 2018
    The Ohio Department of Transportation recently installed Dura-Line’s 7-way FuturePath fibre network alongside its 35-mile Smart Mobility Corridor - a limited access, four-lane highway designated by the state as a test site for smart transportation technology. As transportation networks increasingly rely on connectivity and the availability of big data, communications infrastructure needs to provide sufficient bandwidth and speed to support equipment for monitoring traffic and self-driving cars and convey
  • Investment in pedestrian, cycling initiatives pays off
    June 30, 2014
    Five years after the Non-motorised Transportation Pilot Program (NTPP) was established to measure the impact of investment in walking and cycling initiatives, the US Federal Highway Administration (FHWA) has reported a 22.8 per cent increase in walking and a 48.3 per cent increase in cycling, while an estimated 85.1 million vehicle miles were avoided. The NTPP provided approximately US$25 million each to four pilot communities (Columbia, Missouri; Marin County, California; Minneapolis area, Minnesota; an
  • Details of new Dartford Crossing safety system unveiled
    January 21, 2015
    Since it launched on 30 November last year, Dart Charge has already helped to speed up journeys by removing the need to stop at a barrier to pay the Dartford Crossing charge. To get the most benefit from the changes, the UK Highways Agency has developed a new way of identifying and managing over-height vehicles and dangerous loads before they enter the tunnel, a job that until now was carried out at the payment barriers. All major tunnels have rules about what substances can be taken through them an