Croix-Rousse demonstrates art of tunnel safety

How do you expand a tunnel when it has reached its traffic limit? Build another tunnel in parallel to it. That, at least, is what Lyon did and opened the 1.7km Croix-Rousse dual-tunnel system in 2013. The smaller, new €283 million tunnel has become a symbol of Lyon’s intention to reinvent itself as one of France’s most innovative mobility centres, said Mathieu Hermen, head of operations at La Metropole de Lyon. Construction of the original two-lane tunnel under one of the city’s most densely populated arro
December 6, 2018 Read time: 3 mins
Eco-tunnel: the Croix-Rousse in Lyon
How do you expand a tunnel when it has reached its traffic limit? Build another tunnel in parallel to it. That, at least, is what Lyon did and opened the 1.7km Croix-Rousse dual-tunnel system in 2013. The smaller, new €283 million tunnel has become a symbol of Lyon’s intention to reinvent itself as one of France’s most innovative mobility centres, said Mathieu Hermen, head of operations at La Metropole de Lyon.


Construction of the original two-lane tunnel under one of the city’s most densely populated arrondissements started in 1939. Work was halted by the Second World War when the site was used as an air-raid shelter. It was finally opened in 1952. The original tunnel has a speed limit of 50kph and nearly 50,000 vehicles use it daily.

Physical separation


A concrete barrier was installed in 1998 to physically separate the two lanes, both of which have a useable width of almost 6m. But physical deterioration by then was starting to be a concern, as well as a lack of escape tunnels, which meant something had to be done.

Much consultation ensued to consider options such as double-decking the original tunnel and widening it. But the chosen option was to make a parallel tunnel and use it for more eco-friendly modes of mobility.

The single vehicle lane is for public transportation – buses – and there is a separate two-way cycle path as well as a wide separate pedestrian path. Thanks to 11 cross-galleries the latest 10m-wide tunnel acts as the escape tunnel for the original vehicle tunnel, explained Hermen. Around 2,300 cyclists and 2,000 pedestrians use the new tunnel each day.

The busway – a one-way direction - can be later adapted for use by a tramway should the city decide to go down that route. Only one bus at a time is allowed through the tunnel in case of a breakdown that could snarl up other buses behind the stricken vehicle.

Emergency escape


A barrier, almost 1m high, separates the busway from the cycle lane. But there are many sections of the barrier that will slide open in the case of an emergency, should people need to escape the tunnel. The escape cross-galleries are sealed by heavy doors that are motorised for ease of opening from inside. There are also digital temperature readouts inside the galleries so occupants know, in the case of a fire, what the temperature is right behind the door. A main control centre for all motorways and the tunnels in Lyon lies some way away, but there is a small operations control centre at one end of the new Croix-Rousse for monitoring an emergency situation on-site.

During a technical tour of the Croix-Rousse ‘eco-tunnel’, delegates experienced the three-dimensional video show that covers much of the infrastructure’s walls. The artistry and imagination has turned a city commuter’s daily experience into a must-visit for many tourists to Lyon.

Related Content

  • Rochester solves $8.5m transit question
    October 22, 2018
    RTS in Rochester, New York, saves by working with Conduent to upgrade its CAD/AVL systems rather than ripping them up and replacing them. Andrew Bardin Williams hops on for a ride. What to do, what to do?” It’s a question every transportation official must ask when faced with legacy assets, equipment and software that are nearing the end of their useful life. Nothing lasts forever, right? Freeways need to be repaired, bridges replaced, traffic management software updated and railway cars turned into
  • Mario Cuomo Bridge: an ITS hotbed
    January 4, 2021
    The 3.1-mile Governor Mario M. Cuomo Bridge over the Hudson River in New York State is not just a massive engineering project – it is an ITS hotbed too. Phil Riggio of HDR tells Adam Hill why
  • IBTTA 2010 meeting focuses on sustainability
    February 2, 2012
    Ken Philmus, chief meeting organiser, talks about what attendees can expect to see at this year's IBTTA annual meeting and exhibition
  • Big data bonus for Dublin’s buses
    August 19, 2014
    Dublin’s smart research partnership speeds buses More than 50% of people travelling into and across the Irish capital rely on public transport, and four out of 10 these use buses meaning Dublin Bus carries some 120 million passengers a year.